Red Wood Deck and Railings
1987: Red Wood Deck
East Northport, NY
ITEM- DP - 01
- Stage 1 - Property Plan and site survey.
- Stage 2 - Site preparation to include removal of over grown shrub, bush and trees with our Bobcat. All original debris was hauled to land fill and discarded.
- Stage 3 - Installation of concrete pillars, footings, joists and main supports.
- Stage 4 - Installation Red Wood Planking.
- Stage 5 - Installation of Railing.
|
|